Project Mercedes Benz

Total Electrical Value – $ 87K

Project was achieved on schedule and on budget
Our scope of works was as follows: –
Power systems
Supplied and installed new power circuits and power points throughout the office space, workshop and showroom including the installation of safety switches to the switchboards where required.

Lighting

  • Upgraded lighting throughout office area, showroom and workshop.• Upgraded lighting throughout office area, showroom and workshop.
  • Supplied and installed upgraded emergency lighting system to meet current standards.

Illuminated Signage

  • Supplied and installed power for the illuminated fascia signage and feature sign on the corner including automatic dusk till dawn controls.

Telecommunications System

  • Upgraded existing 600 series phone outlets to current RJ12 style.
  • Upgraded existing 600 series phone outlets to current RJ12 style.
  • Supplied and installed new phone points and cabling as required to the new office space, workshop and showroom.
  • Relocated existing main KRONE rack from the boardroom to the new PABX room including new 50 pair cable from relocated KRONE rack to MDF.

Structured Cabling System

  • Disconnection and removal of existing cat5 system.• Disconnection and removal of existing cat5 system.
  • Relocation of existing data cabinet from board room to new PABX room.
  • Supply and installation of new Clipsal Titanium Cat6 patch panels to upgrade the existing communications cabinet to Cat6.
  • Installation of new cat6 cabling from new patch panels on new catenary wires to new cat6 outlets throughout office space, showroom and workshop.
  • Supplied and installed Hager Blue Cat6 data outlets to cabling.

MATV System

  • Supplied and installed new Splitter into main TV coaxial cable.
  • Supplied and installed new Splitter into main TV coaxial cable.
  • Supplied and installed new RG6 coaxial cable throughout office.
  • Supplied and installed new RG6 screw type TV outlet plates as required.